Business Jet Landing Gear Overhaul: How to Plan It Before the Calendar Plans It for You

5m
8 min read

Most owners know roughly when their engines are due. Far fewer can say, without looking, when their landing gear is due for overhaul. That is a problem, because a gear overhaul is one of the longest single maintenances events a business jet goes through, and on many aircraft, it is the calendar, not hours or landings, that sets the deadline.


A jet that flies 200 hours a year can reach a gear limit with plenty of cycles left on paper. If nobody has the date on the planning sheet, the first warning is a tracking report or an inspection quote, and by then the good options (an exchange set, a shop slot that lines up with your heavy check, time to approve findings) may already be gone.


This guide is written from the hangar floor for owners, DOMs and flight departments. It covers how to find your real due date, what drives cost and downtime, and how to decide between overhauling your own gear and using an exchange. Intervals and requirements vary by aircraft, so always confirm specifics against your aircraft's maintenance manual, maintenance planning document and the manufacturer's current revisions.


Years, cycles or both: finding your real due date

Landing gear limits are usually expressed as calendar time, landing cycles, or both, whichever comes first. A cycle is one takeoff and landing. The numbers differ widely by manufacturer and model, which is why you should never borrow a figure from a different aircraft.


As an illustration of how much they vary, AAI, a landing gear repair station, published these examples in December 2025:

  • King Air: inspection or overhaul every 6 years or 8,000 cycles, whichever comes first

  • Hawker: every 12 years or 5,000 cycles

  • Challenger 300 and 600 series: limits stated in months

In a January 2026 follow-up, AAI described the Challenger 300 and 600 series (except the 601) as needing a detailed inspection at 96 months and a restoration (overhaul) at 192 months, then restoration every 96 months after that, with the Challenger 601 on a 60-month detailed inspection and 120-month restoration. These are AAI's published summaries, not a substitute for the current Bombardier maintenance requirements for your serial number. Confirm before you plan.


The practical point: on a business jet that averages perhaps a few hundred landings a year, a cycle limit in the thousands may be decades away while the calendar limit arrives on schedule.


Where the due date actually lives

Your due date should come from three places that agree with each other:

  1. The manufacturer's current maintenance program for your model and serial number, including any revisions.

  2. Your tracking program (whatever service your aircraft uses), showing the gear and its life-limited parts with calendar and cycle status.

  3. Your maintenance records. Under 14 CFR 91.417, owners must keep records that include the current status of life-limited parts. For gear, that means knowing the start date and cycle count each limit is measured from, which is usually the date of manufacture or the last overhaul.

If those three sources disagree, sort it out now, not when the gear is on the bench. A missing overhaul certificate, an undocumented part change or a gap in cycle history is far cheaper to resolve on your timeline. Our guide to auditing business jet maintenance records covers how to check for these gaps.


Why gear overhauls run long

An overhaul is not a single task. The gear is removed, completely disassembled, stripped, and inspected for wear, corrosion and cracks using visual, dimensional and nondestructive methods. Worn, corroded and life-limited parts are replaced or repaired, protective finishes are reapplied, and the assembly is rebuilt to the manufacturer's specifications and returned with the appropriate release documentation from a certificated repair station.

Published industry sources point to the same set of delay drivers:

  • Every sub-component has to finish together. AAI's March 2026 article puts it bluntly: if even one sub-component lags behind, the aircraft stays grounded.

  • Findings that need specialist repair. AAI notes that rechroming a damaged piston typically takes 30 to 45 days on its own.

  • Parts and consumables. Precision Aviation Group lists actuators, trunnions, bushings, seals and specialized fasteners as common availability problems. AAI points out that even greases and coatings can stop a job if they are out of stock.

  • Obsolescence. When OEM parts or repairs are slow or unavailable, a DER-approved alternative repair may be the path, which takes time to arrange.

  • Decisions and approvals. AAI lists quote approvals, payment processing and customer decisions on unexpected damage as common causes of stalled work.

The last item is the one you control completely. A gear set can sit finished except for one approval while a decision waits in someone's inbox.


What tends to drive the findings

AAI's January 2026 article on Challenger gear lists the usual wear points: shock strut seals and attachment points, bushings and bearings worn by repeated retraction, actuator pins and lugs, chafed or leaking hydraulic lines and fittings, and corrosion from moisture, de-icing fluid and runway contaminants. Aircraft that sit outside, operate from coastal or winter fields, or fly infrequently tend to give corrosion more opportunity. That is an observation, not a rule; your shop's inspection is what decides.


It is also worth knowing that a second overhaul is not a repeat of the first. In AviTrader's February 2026 feature, an MRO executive notes that first and second overhauls can differ considerably in scope, material demand and cost. If your last gear overhaul was easy, do not budget the next one off that invoice.


Exchange or overhaul your own gear?

For a single aircraft, this is usually the biggest planning decision.

Overhauling your own gear keeps your serial-numbered components and their history. Downtime is the overhaul turn time plus removal and installation, and any surprise finding extends it.

An exchange (or rental) gear set lets the aircraft go back into service once the replacement set is installed, while your gear is overhauled separately or swapped outright. The tradeoffs are cost, availability for your type and the paperwork on the incoming set.

Questions that help decide:

  • How long can the aircraft realistically be down, and what does each extra week cost you in cancelled trips or charter commitments?

  • Is an exchange set even available for your model at the time you need it? Availability varies by type and can be limited, so ask early.

  • How is the exchange priced: flat fee, plus overhaul cost of your core, plus charges for beyond-economical-repair findings?

  • What will the incoming set's records show? You want complete, traceable history for the gear and its life-limited parts, because it becomes your aircraft's history.

  • If your own gear is overhauled, can rental components (an actuator, a nose gear) cover a long-lead item? AAI's March 2026 article describes using a rental actuator to keep an aircraft flying while its own actuator piston was being rechromed.

There is no universally right answer. A flight department with a busy schedule and a single aircraft may value an exchange highly; an owner who flies seasonally may prefer to overhaul their own gear during a planned layup. If repeat component removals are part of your planning picture, our article on stopping repeat APU removals and AOG surprises covers the same approach for another big-ticket system.


A practical planning timeline

This is a suggested framework, not a regulatory requirement. Adjust it to your aircraft and your shop.

18 to 24 months out

  • Confirm the gear due date from the maintenance program, tracking and records, and resolve any discrepancies.

  • Check whether the gear limit falls near a major inspection. Combining them is one of the simplest ways to save downtime, and AAI recommends scheduling overhauls alongside major inspections for that reason. Our article on how far in advance to book a heavy inspection covers the same booking logic.

12 months out

  • Get quotes for both your-gear overhaul and exchange, if available.

  • Ask the shop which parts they commonly replace on your type and whether they can pre-order them.

  • Budget a contingency for findings rather than planning on the base quote.

6 months out

  • Book the slot and, if using an exchange, reserve the set.

  • Agree in writing how findings will be approved: who can approve, what dollar threshold, and how fast.

During the event

  • Respond to findings quickly. Ask for photos and the repair options with cost and time for each.

  • Ask for status by sub-component, not only an overall percentage.

After return to service

  • Make sure the release paperwork, life-limited part status and new start dates are in your records and tracking before the aircraft flies. This is the baseline for the next overhaul.

A hypothetical example

This is an illustration, not a real customer case. A midsize jet is due for a calendar-based gear overhaul about four months after its next heavy inspection. Planned separately, that means two removals, two downtime periods and, most likely, the gear event landing in the middle of the busy season. Moving the gear work into the heavy inspection costs some calendar life, because the gear goes in a few months before it had to, but it collapses two outages into one and gives the shop the gear while the aircraft is already on jacks. Whether that trade makes sense depends on the aircraft, the quote and the schedule. The point is that it can only be considered if someone noticed the dates a year earlier.

Frequently asked questions

Is landing gear overhaul based on hours, cycles or years?

It depends on the aircraft. Limits are commonly calendar time, landing cycles or both, whichever comes first. Check your manufacturer's maintenance program for your model and serial number.

How long does a business jet landing gear overhaul take?

There is no single figure. It depends on the type, the shop, parts availability and what is found. Individual repairs can take weeks on their own; AAI cites 30 to 45 days just to rechrome a damaged piston. Ask your shop for a realistic range on your type and what typically extends it.

Can I combine a gear overhaul with a heavy inspection?

Often, yes, and it can save significant downtime. You may give up some remaining calendar life by doing the gear early. Plan it with your shop well in advance.

What records do I need for landing gear?

At minimum, the current status of life-limited parts as required by 14 CFR 91.417, plus the release documentation from the last overhaul and a traceable cycle history. Missing or unclear documentation can force costly part replacement.

Is an exchange gear set worth it?

It can be when downtime is expensive and a set is available for your type. Compare total cost (exchange fee, core charges, findings) against the cost of the extra days out of service.

The bottom line

Landing gear overhauls rarely surprise people because the work is unexpected. They surprise people because the date was not on anyone's radar. Confirm the due date from the program, tracking and records, line it up with your next major inspection where it makes sense, decide on exchange versus overhaul early, and agree how findings will be approved before the gear comes off.

If your gear is due in the next two years and you want help building a plan around your schedule, talk to the EJS team.

Question for you: When did you last check your landing gear due date, and was it the calendar or the cycles that drove it?